In the 35 . Calendar week we have the interior space, work on the Viega Steptec system continued and expanded with the installation of the Lebast started Lehmorange earthen walls. In addition, the wiring of ETS has continued.
on the façade with the installation of Porextherm Vacupor Vacuum insulation has been started and the relocation of the Elasto-Veral Icopal roof rail and the cover of the Intersection points with Prefa aluminum roofing profiles by Martin Hafner largely complete.
We also have the support structure for the balcony on the south side of OpenOffice created and can begin in the next few days with the occupation of Kosche Kovalex boards.
For more photos please click